CALAX Silang Aguinaldo section 91% done, opens Sept 2023

CALAX Silang Aguinaldo section 91% done, opens Sept 2023
Work on CALAX Subsection 4 is nearly finished
Last June, Metro Pacific Tollways-South (MPT-South) announced that work on the Silang Aguinaldo section of the Cavite Laguna Expressway (CALAX) is 80% complete. This means motorists bound for Cavite can get to Aguinaldo Highway quicker via the soon-to-be-finished 3.9 km segment.
Fast forward to August 2023 and it won't be long before the Silang Aguinaldo section (AKA Subsection 4) of CALAX will be completed. This comes after MPT South recently announced that work on the aforementioned section is now 91% done. What's better is that they plan to open it to the public next month.
Currently, work on the Aguinaldo Silang section is focused on the construction of toll facilities, road lights, signage, and sound barriers. Moreover, preparations are also being made for the electronic toll collection system as the new segment is expected to cater to an additional 5,000 motorists daily.

Once the new segment is officially opened, it will greatly enhance travel convenience for motorists heading from Laguna to Silang and Tagaytay, and vice versa. The new segment will also follow the company's vision for environmental safety, sustainable tourism, as well as green technology.
Like the currently operating portions of CALAX, Subsection 4 will also have solar panels on its toll plaza which generates power for the plaza's operations. Moreover, it has LED light fixtures on the roadway to enhance energy efficiency, as well as offset carbon emissions.
Related Posts

CALAX Subsection 3 Governor's Drive no longer toll-free
After being toll-free for three months, TRB announces toll rates for CALAX Subsection 3

New 7.8 km section of CALAX extends to Governor's Drive in Cavite
New CALAX Subsection 3 is toll-free for an entire month, says President Marcos Jr.

Forget Tagaytay: Discover the delightful Cafe Agapita, a hidden gem in Silang
Cafe Agapita, literally just a few kilometers from the CALAX Silang-Aguinaldo interchange

CALAX Governor's Drive Interchange nearing 40% completion
Upcoming 8.64-km segment is expected to decongest traffic in Governor's Drive and General Trias in Cavite

ICYMI: CALAX Silang Aguinaldo section no longer toll-free
TRB approves toll rates for CALAX Silang Aguinaldo section

MPT South donates 900 school kits for Brigada Eskwela 2025
Brigada Eskwela: Sama-sama Para sa Bayang Bumabasa